The California Public Utilities Commission (CPUC) has granted a request from the City of Chino Hills to put underground a segment of Southern California Edison's Tehachapi Renewable Transmission Project.

The CPUC agreed with the City's assertion that the design of the above-ground line "ignores community values and places an unfair and unreasonable burden on residents."

Currently, the 3.5-mile segment of the 500 kV transmission line running through Chino Hills consists of massive transmission towers reaching nearly 200 feet tall and set in a narrow 150-foot right of way. The CPUC's decision "rectifies that disproportionate burden and finds that it is in the public interest to construct an underground alternative based on a single circuit, two cables per phase design using cross-linked polyethylene cable."

It will cost approximately $224 million to underground the Chino Hills portion of the line.


Hse SandyHook
Latest Top Stories

NERC CIP Version 5: Security In The Age Of Cyber Warfare

An expert from Waterfall Security Solutions finds that the latest standards are a leap forward for cybersecurity.


Does Income Determine Who Benefits The Most From Smart Grids?

According to the Smart Grid Consumer Collaborative, low-income consumers may be at a disadvantage.


Accenture And Siemens Form Smart Grid Joint Venture

OMNETRIC Group will help utilities improve energy efficiency, grid operations and reliability.


Maine Public Utilities Commission: Smart Meters Are Safe

According to a report by the commission, there is no direct link between smart meters and health issues.


Report: Global Solar Deployment Topped Wind In 2013

Research firm Clean Edge finds that solar surpassed wind for the first time since it began tracking international markets in 2000.

S&C Electric_id176
edf_id