European grid operator TenneT says construction has begun on the HelWin2 platform, an offshore grid connection that will transport 690 MW of wind energy from offshore wind farms to the mainland.

The HelWin2 project is being developed jointly by Heerema Fabrication Group and Siemens, the main contractor for the HelWin2 project.

The platform will connect a large wind farm cluster in the German North Sea. It will receive alternating-current electricity from wind farms and convert it into direct-current electricity before transporting it onshore via subsea cables. The 98-meter by 42-meter steel structure of the platform topsides will be more than 27 meters tall and weigh over 10,000 metric tons.

The first offshore wind farm that will be connected to the platform is Amrumbank West. The grid connection runs 45 km across land from the converter station in Buttel to the coast, and extends another 85 km from the landing point in Busum to the offshore converter station.


Hse SandyHook
Latest Top Stories

Does Income Determine Who Benefits The Most From Smart Grids?

According to the Smart Grid Consumer Collaborative, low-income consumers may be at a disadvantage.


Accenture And Siemens Form Smart Grid Joint Venture

OMNETRIC Group will help utilities improve energy efficiency, grid operations and reliability.


Maine Public Utilities Commission: Smart Meters Are Safe

According to a report by the commission, there is no direct link between smart meters and health issues.


Report: Global Solar Deployment Topped Wind In 2013

Research firm Clean Edge finds that solar surpassed wind for the first time since it began tracking international markets in 2000.


HEM Is Key For Utilities To Maintain A Competitive Edge

According to a report by Lux Research, automated meters, electricity rates and renewable energy are crucial to the success of home energy management.

S&C Electric_id176
edf_id