Lone Star Transmission LLC, a subsidiary of NextEra Energy Inc., has energized approximately 330 miles of new 345 kV transmission lines and associated transmission facilities. The project runs from Scurry County, northwest of Abilene, Texas, to Navarro County, south of Dallas. Four circuits and five substations are a part of the new infrastructure.

Lone Star's transmission lines are contributing to the state's transmission grid improvement program, which will see the addition of approximately 2,300 miles of 345 kV lines designed to deliver power from the Competitive Renewable Energy Zones (CREZ) in West Texas and the Texas Panhandle to the Dallas/Fort Worth area and other population centers. Lone Star says it is the first new transmission utility to energize its CREZ facilities.

The company says it used more than 2,500 spun concrete monopoles to complete the project, which helped reduce the project's visual impact and land needs without adding costs.


Hse SandyHook
Latest Top Stories

SaskPower Halts Smart Meter Installations Following Fires

The Canadian utility has suspended its smart meter deployment as it investigates half a dozen fires associated with the meters.


New Study Underscores Value Of Customer Engagement, Ranks Most-Trusted U.S. Utilities

According to the report, which analyzes 125 utilities across the country, earning a customer's trust can lead to monetary gains.


Washington State Doles Out Cash For Utility Energy Storage Projects

Three utilities have been awarded millions of dollars in grants to explore energy storage technology that could help integrate renewable and improve the power grid.


Utilities Reveal Just How Much Customers Are Saving With Energy Efficiency Programs

Two U.S. utility companies have issued progress reports and solid numbers regarding their respective initiatives.


Middle East And North African Countries To Spend Billions On Smart Grids, Solar Integration

According to a new report from Northeast Group LLC, the MENA region will make big investments to modernize the grid and add more solar power by 2024.

S&C Electric_id176
edf_id180